Data centers could reach 12% of U.S. electricity by 2028: the demand already hiring Brazilian suppliers

U.S. data center power use tripled in a decade and could triple again by 2028. Construction of these facilities is at a record, while transformers, generators and grid equipment are in short supply. We show where the demand is and how Brazilian suppliers are already positioned.

Data from 2014 to October 20266-minute readPublished October 23, 2026

4.4%

of U.S. electricity was consumed by data centers in 2023

LBNL / DOE, Dec 2024

up to 12%

projected share in 2028 in the high scenario; 6.7% in the low one

LBNL / DOE, Dec 2024

US$85bn

annualized pace of data center construction in August 2026, up 73% in a year

U.S. Census Bureau

4 years

maximum wait for high-capacity power transformers, according to PwC analysts

pv magazine USA, May 2026

Executive summary

  1. Demand is structural. Data centers used 176 TWh in 2023, 4.4% of U.S. electricity, and the Department of Energy projects 325 to 580 TWh in 2028, or 6.7% to 12% of national consumption.
  2. The money is already on site. Data center construction reached a record annualized pace of US$85 billion in August 2026, 73% above a year earlier, while factory construction fell about 20%.
  3. The grid is the bottleneck. The EIA expects record power use in 2026 and 2027, large transformers can take up to four years to arrive, and demand for generator step-up transformers rose 274% from 2019 to 2025.
  4. Brazilian suppliers are moving. WEG is expanding its Missouri transformer capacity by 50% and announced US$165 million for generators in North America; TSEA starts producing voltage regulators in North Carolina this quarter.

A decade of tripling demand

U.S. data centers used 58 TWh in 2014 and 176 TWh in 2023, with the growth of servers for artificial intelligence behind much of the recent acceleration. For 2028, the Lawrence Berkeley National Laboratory report published by the Department of Energy projects 325 to 580 TWh, depending on the scenario.

Our reading: even the low scenario requires new generation, transmission and grid equipment at a scale that U.S. industry has not been able to supply on its own.

Exhibit 1

Electricity used by U.S. data centers (TWh)

Source: Lawrence Berkeley National Laboratory, United States Data Center Energy Usage Report (U.S. Department of Energy, Dec 2024).

2023

4.4% of the country's power

Data centers already use more than 4% of U.S. electricity.

2028

From 6.7% to 12%

The range projected by LBNL, depending on the adoption scenario.

Our reading

Even the low case strains the grid

Generation, transmission and equipment have to arrive before the demand does.

Record construction, a grid at its limit

Data center construction reached an annualized US$85 billion in August 2026, 73% above August 2025, according to the Census Bureau. In the same month, total construction was 1.7% lower than a year earlier and factory construction about 20% lower.

Power use follows. The EIA projects record consumption of 4,288 billion kWh in 2026 and 4,356 billion in 2027, led by the commercial sector, where data centers are counted.

Exhibit 2

U.S. construction spending, August 2026 against August 2025 (%)

Source: U.S. Census Bureau, construction spending release of Oct 1, 2026 (seasonally adjusted annual rates). Data centers: private category reported by Census.

EIA

Record power use in 2026 and 2027

4,288 and 4,356 billion kWh, against 4,195 billion in 2025.

Transformers

Up to four years of waiting

Lead time cited by PwC analysts for high-capacity units; prices rose about 80% in five years.

Generation

+274% in step-up transformer demand

Between 2019 and 2025, according to Wood Mackenzie.

Who already supplies this wave

Two Brazilian moves and where else the opening is.

Missouri and North America

WEG

Is expanding capacity at its transformer plant in Washington, Missouri, by 50% to serve industry, the grid and data centers. In September 2026 it announced US$165 million to expand generator production in North America, aimed at data centers and critical infrastructure.

North Carolina · US$25M

TSEA Energy

First U.S. plant, in Eden, dedicated to voltage regulators for utilities modernizing the grid. Gradual start in the fourth quarter of 2026, within an expansion plan of more than R$1.1 billion.

Our reading

Where else there is room

Cables, switchgear, steel structures, cooling, generator components and maintenance services follow every megawatt installed. The transformer shortage shows local supply is not keeping pace.

What to do now

  1. Map which of your products serve data centers, generation and the grid in the U.S., and which certifications they need.
  2. Measure your lead time and available capacity against competitors: when the queue is years long, availability sells.
  3. Decide whether to export, assemble or produce close to the customer, with tariffs and state incentives in the math.

Does your product have a place in the U.S. power chain? We answer with numbers.

Speak with a partner about demand, competition and the right entry model.

Speak with a partner

About this article

Prepared by the Marroffino & Partners team of specialists in strategy and U.S. market entry.

To discuss these findings for your company, write to us or book a conversation with a partner.